Dry-In Construction
If you choose to become your own General Contractor, Fireside Log Homes of North Georgia can provide you with "Dry-In Construction." This type of construction will provide you with a complete weather tight shell based on the components of your log home package. The Dry-in is ready to begin upon completion of your foundation. The following is an outline of our standard Dry-in service, which can easily be modified as needed.
- Frame all basement daylight walls and partition walls where needed
- Assemble sub-floor on your foundation to include sill plate, floor joists and plywood decking
- Erect log walls and log siding walls through gables and dormers
- Assemble second floor framing system
- Apply second floor decking material
- Erect rafters, collar and heavy timber trusses where needed for heavy timber roof or conventional framing and trusses where designed for complete roof
- Apply roof sub-decking
- Apply rigid insulation if required
- Apply final sheathing
- Apply felt
- Install exterior windows and doors with exterior trim
- Frame for all fixed glass and trim
- Install interior heavy timber steps
- Install basement temporary steps
- Frame all decks with hand rails, erect covered porch post, cap beams, rafters, decking and felt
- Apply all fascia boards, frame all interior partition walls
|
Turn-key Construction
Fireside Log Homes provides complete turn-key construction services including design, structural engineering, excavation, foundation, framing, complete assembly/erection of your log home package, windows and doors, roofing, decks, HVAC, electrical and plumbing, complete interior to include cabinetry and countertops, flooring, trim, and requested stains or finishes.
- Preliminary blue-lines and preliminary estimate
- Final blueprints and contract quote, terms and conditions
- Acquire permits
- Land clearing and rough grading
- Temporary electric and telephone
- Ditching for electric, phone, TV, water, footings and foundations
- Pour footings and foundations with all below grade mechanical box outs. Water-proof foundations
- Pour footings and foundations
- Backfill to final grade
- Frame sub floor for first level
- Erect log walls
- Build exterior decks and porches with steps if required
- Erect second floor system structural members
- Placement of temporary flooring for walkways on second floor
- Erect rafter, collar ties and heavy timber trusses where needed
- Apply roof sub-decking (1x8 T&G)
- Build dormers
- Install all necessary sub-sheathing on dormers and gables
- Install all necessary log siding on exterior and interior as required
- Apply roof insulation
- Apply final roof sheathing with felt
- Complete roof covering - metal, asphalt, shake Apply second floor
- Frame all interior partition walls
- Build fireplace
- Install windows and doors with all trim
- Install and trim all fixed glass panels
- Install heavy timber steps with railings
- Apply all fascia boards, exterior trim and soffits
- Electrical, plumbing, HVAC, and other mechanical rough-ins
- Add interior wall insulation
- Install all interior wall covering
- Install hardwood floor
- Install interior doors and trim
- Complete all floor and attic insulation (if applicable)
- Install all necessary guttering (if applicable)
- Apply exterior paint or stain
- Install cabinets and vanities with tops
- Install screen on screened in porch
- Install plumbing fixtures and electrical fixtures
- Install appliances, stove, dishwasher, disposal
- Install hardware
- Install bath mirrors
- Install carpet as required
- Final clean-up MOVE IN!!!!!
|